This project for Jersey New Waterwork has a capacity of 2 MLD permeate, blended with 2 MLD reservoir water.
The Site is located adjacent to the Le Mourier Reservoir, in La Vallee des Mouriers on the island state of Jersey.
The Site comprises an existing Pump Station, Tank, Electricity Substation and other associated works serving the Le Mourier Valley Reservoir